Bouwupdate juni
December construction update
Contractor Loffts is on the job
Construction work at our resort is in full swing! Contractor Loffts is working hard to build new homes, currently there are 14 home on site and all of these homes are being completed. The Loffts plant also produces new homes, which will soon be placed on site. This means we are making great strides in creating a beautiful recreational environment for both our future residents and tenants.
Infra Kooiker lays the foundation for the future
Infra Kooiker is also busy installing all of the cables and pipelines, an essential step in the infrastructure of Phase 1 as well as Phases 2 and 3. This work will ensure that all homes and facilities can be perfectly connected to future utilities.
First homes already available in the HUB rental environment!
The first homes of type Welvaren and Koperbaay are now listed on the HUB rental platform so that they can be rented out during the summer period. We look forward to a wonderful summer break with happy tenants and high occupancy.
Sustainability first: construction of frog habitats to start soon
By the end of this month, we expect to begin construction of special frog habitats so that frogs can migrate naturally and safely. This initiative perfectly fits within the sustainable vision of our eco resort. We combine leisure with nature conservation and ensure a harmonious balance between people and the environment. In addition, depending on the progress, the construction of the retaining walls for the 4 “De bezinning” type properties can also be started.
Demolition of old restroom building scheduled for February
To make room for new development, the demolition of the old restroom building may be scheduled this month. This will mark another step in the modernization and optimization of the resort.
Finally
The coming weeks will be characterized by further construction developments, during which, of course, we will continue to keep you informed. Do you have any questions, or would you like more information about the progress? Please feel free to contact us.


Nieuwe aannemer en eerste casco’s.
Per afgelopen maand werkt AntesZ Bouw in plaats van LOFFTS aan het project. De overdracht verliep soepel, zonder dat jij daar iets van merkt. Inmiddels zijn drie casco-woningen (type Koperbaay) op hun fundering geplaatst. Dit is de ruwbouwfase: zodra de casco’s wind- en waterdicht zijn, starten we met:
• Binnenwanden
• Leidingen en gevelisolatie
• Plaatsen van ramen en afwerking van installaties
Groen rondom de woningen
Voor fase 2 en 3 zijn de grasmatten ingezaaid. Binnen enkele weken kleurt het terrein frisgroen. Dankzij speciaal gras genieten we al in juni van een mooi gazon rond de eerste woningen.
Vrijgave kikkerhabitat en waterwoningen
Onze ecoloog heeft het voormalige kikkergebied vrijgegeven; de kikkers zijn verhuisd naar een nieuw moerasgebied. Nu dit terrein beschikbaar is en de vergunningen voor de vier waterwoningen van het type Bezinning gereed zijn, gaan we over tot het bouwrijp maken. We gaan nu aan de slag met alle infrawerkzaamheden, zoals het egaliseren van de grond en het aanleggen van kabels en leidingen.
Deze woningen krijgen straks een directe verbinding met het water, houten vlonders en royale glaspartijen die het landschap binnentrekken.


Tijdelijk restaurant: pop-up met succes
Ons tijdelijke restaurant met terras is geopend en werd goed bezocht door omwonenden en voorbijgangers. Dit restaurant is alvast een voorproefje van het permanente paviljoen: lokaal, groen en smaakvol.
In de komende weken zetten we de volgende bouwfases voort en houden we je uiteraard op de hoogte. Heb je vragen of wil je meer weten over de voortgang? Neem dan gerust contact met ons op.